What does a Class 3 Estimate typically correspond to in terms of project definition level?

Prepare for the AACE Certified Cost Technician Exam. Study with flashcards and multiple choice questions, each with hints and explanations. Secure your certification with confidence!

Multiple Choice

What does a Class 3 Estimate typically correspond to in terms of project definition level?

Explanation:
A Class 3 Estimate is typically associated with a project that has a defined scope and a moderate amount of detail, generally ranging from 30% to 70% project definition. This level of estimate is often used during the early phases of a project when there is a reasonable amount of information available to create a budget but not enough for precise calculations. Such estimates are valuable when a project is moving towards more detailed design and planning phases, allowing stakeholders to understand financial implications and make informed decisions. Additionally, Class 3 Estimates are appropriate for feasibility studies and budgeting purposes, providing a solid foundation as the project definition evolves. In contrast, the other ranges presented do not align with the established definitions for Class 3 Estimates. The percentages that indicate lower project definition levels suggest either less certainty or are less detailed than typical Class 3 benchmarks.

A Class 3 Estimate is typically associated with a project that has a defined scope and a moderate amount of detail, generally ranging from 30% to 70% project definition. This level of estimate is often used during the early phases of a project when there is a reasonable amount of information available to create a budget but not enough for precise calculations.

Such estimates are valuable when a project is moving towards more detailed design and planning phases, allowing stakeholders to understand financial implications and make informed decisions. Additionally, Class 3 Estimates are appropriate for feasibility studies and budgeting purposes, providing a solid foundation as the project definition evolves.

In contrast, the other ranges presented do not align with the established definitions for Class 3 Estimates. The percentages that indicate lower project definition levels suggest either less certainty or are less detailed than typical Class 3 benchmarks.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy